Certifying category II PPE: the real timeline, from quote to EU type-examination certificate

Category II PPE: the notified body's lead time runs from a complete file. Working-day calculation, checklist and the date to give the French authority.

Certifying category II PPE: the real timeline, from quote to EU type-examination certificate

For category II personal protective equipment (PPE), CE marking requires a notified body, which issues an EU type-examination certificate. After an inspection by the DDPP (the local consumer protection authority in France), the authority asks a simple question: when will the products comply? The answer depends far less on the date the quote was signed than on the day the notified body receives a complete file.

This article starts from an anonymised client case and sets out the method in seven steps: check the body, read its terms, prepare the file, count working days, stagger the products, give the authority a date you can keep, and say nothing to consumers before the certificate is issued. The firm assists businesses with regulatory compliance reviews, before and after an inspection.

The case: quotes signed, nothing sent a month later

Anonymised client case. After an inspection, a company signs quotes with a notified body. The announced lead time (around 45 working days of testing, then 10 working days for certification) only runs from receipt of the samples, the technical file, the instructions and full payment. One month after signature, nothing has been sent. The date to give the authority depends on the shipping date, not on the date of the quote.

The manager believes certification started when the quote was signed. For the notified body, the clock stays at zero until the file is complete, whether samples, instructions or payment are missing. Every week lost before shipping is lost at the end as well, and public holidays can add to it. If a date has already been given to the authority on the basis of the quote, it will have to be corrected.

Why category II PPE needs a notified body

Regulation (EU) 2016/425 on personal protective equipment classifies PPE by the risks it protects against (Annex I). Category I is a closed list of minimal risks, including superficial mechanical injury. Category III covers risks that may cause death or irreversible damage to health. Category II covers every other risk and applies by default.

Under Article 19, category II requires an EU type-examination (Module B, Annex V) by a notified body, followed by conformity to type based on internal production control (Module C, Annex VI). Article 8(2) sets the order: technical documentation, then the conformity assessment procedure, and only once conformity has been demonstrated, the EU declaration of conformity and the CE marking. Article 17 requires the CE marking to be affixed before the product is placed on the market; the notified body's number only follows it for category III.

In France, DGCCRF officers (including DDPP officers) have power to investigate breaches of the regulation (Labour Code, Article L. 4311-6). Displaying or selling PPE that has not undergone the conformity assessment procedure is an offence punishable by a fine of EUR 50,000, doubled for a repeat offence (Labour Code, Article L. 4746-1, 1°), subject to the Criminal Code rules on companies. The certification timeline therefore sets the date on which sales can resume.

Step 1 - Check that the body is notified for your type of protection

Notified bodies are notified by Member States to the Commission and to the other Member States (Article 20). The Commission assigns each one an identification number and publishes the list of bodies with the activities for which they are notified (Article 29). That list is available in the Commission's NANDO database (New Approach Notified and Designated Organisations).

Check three points: the body is notified under Regulation (EU) 2016/425, it is notified for EU type-examination (Module B), and its scope covers your type of product and risk. A testing laboratory, even an accredited one, does not issue an EU type-examination certificate unless it is notified. A notified body must be established under the national law of a Member State and have legal personality (Article 24(2)); a body outside the EU offering "CE certification" does not, in principle, fill that role, subject to any international agreements concluded by the EU. A notified body may subcontract tasks such as testing, with the client's agreement, and remains fully responsible for them (Article 26). Whether tests already carried out elsewhere can be used is a question to raise before signing.

Step 2 - Read the terms and conditions before signing the quote

Under the terms of many notified bodies, signing the quote means accepting their terms and placing a firm order, and 100% payment upfront is often required. The lead time usually runs from receipt of everything requested. As far as we can see, the regulation sets no processing time for notified bodies; it only requires proportionate assessments that avoid unnecessary burdens on economic operators (Article 32). The lead time in the quote is a contractual, often indicative, commitment.

  • Starting point: receipt of the complete file, receipt of payment, or validation of the file by the body, which can add several days.
  • What "complete" means: list of documents, number of samples per size and model, document format, language of the instructions.
  • Failed test: whether a new test is charged extra, and whether the lead time restarts in full or only for that test.
  • Certification time after testing ends, and the body's closure periods.

These clauses set the date you will be able to give the authority. Having a lawyer review them at this stage avoids promising a date that is not in your hands.

Step 3 - Put together a complete file before shipping anything

The application for EU type-examination is lodged by the manufacturer with a single notified body of its choice (Annex V, point 3). The manufacturer is the person who manufactures PPE, or has it designed or manufactured, and markets it under its own name or trademark (Article 3(4)). The application includes the manufacturer's name and address (and those of the authorised representative if it applies), a written declaration that the same application has not been lodged with another body, the technical documentation described in Annex III and specimens representative of the intended production. The body may ask for more specimens.

In practice, notified bodies often also ask for French-language instructions approved before printing, draft marking and labelling, samples for each size, and sometimes preliminary tests, for example colour fastness to perspiration under ISO 105-E04. The regulation requires instructions in a language set by the Member State (Article 8(7)); in France, PPE sold without instructions, or with incomplete instructions or instructions not written in French, exposes the seller to a fifth-class petty offence fine (Labour Code, Article R. 4746-1).

Table 1 - Checklist of a complete file before shipping

Item Expected content Basis or source Done
Application for EU type-examination In the manufacturer's name, with its address (and the authorised representative's if it applies) Reg. 2016/425, Annex V, point 3(a) Yes / no
Written declaration The same application has not been lodged with any other notified body Annex V, point 3(b) Yes / no
Technical documentation Description and intended use, risk assessment, applicable requirements, drawings, standards, test reports, production methods Annex III Yes / no
Instructions in French Complete version, approved by the body before printing Art. 8(7); Labour Code, R. 4746-1; body's request Yes / no
Draft marking and labelling Model and batch identification, manufacturer's name and address, no CE marking before the certificate Body's request; Art. 17 Yes / no
Specimens Representative of production, enough per size and model Annex V, point 3(d) Yes / no
Preliminary tests requested For example colour fastness to perspiration (ISO 105-E04), if the body asks Body's request Yes / no
Payment Amount and terms in the quote (often 100% upfront) Terms and conditions Yes / no
Proof of shipping and acknowledgement of receipt Date the complete file was received, starting point of the lead time Terms and conditions; evidence for the authority Yes / no

Step 4 - Count in working days, public holidays excluded

In the case above, the body announced around 45 working days of testing, then 10 working days for certification: 55 working days from receipt of the complete file, which is eleven working weeks plus the public holidays in the period. The dates below assume that the complete file is received on the date shown, that the count starts on the next working day, that the body does not close and that no test has to be repeated. They are orders of magnitude.

Table 2 - Calculation examples (45 + 10 working days, order of magnitude)

Complete file received End of testing (45 working days) Certificate (10 more working days) Public holidays excluded
Monday 30 November 2026 Around Wednesday 3 February 2027 Around Wednesday 17 February 2027 25 December 2026, 1 January 2027
Monday 14 December 2026 Around Wednesday 17 February 2027 Around Wednesday 3 March 2027 25 December 2026, 1 January 2027
Monday 4 January 2027 Around Monday 8 March 2027 Around Monday 22 March 2027 None

Between receipt on 30 November and receipt on 4 January, the certificate moves back by about five weeks, from 17 February to 22 March. In the case above, the month lost between signing the quotes and shipping is lost almost entirely at the end. A failed test, a request for extra specimens or instructions to be redone can push the date further, which is why the date is given as "around" and subject to test results.

Step 5 - Stagger the products

Nothing prevents a whole catalogue from being submitted at once. In practice, upfront payment, sample preparation, the body's capacity and the risk of failure often lead businesses to stagger: one or two products a month, or about six months for ten product references (order of magnitude). Start with the products sold in France and those targeted by the authority's findings. Products waiting for their certificate stay off sale in France.

Step 6 - Give the authority a date you can keep, product by product

Where it finds evidence that PPE may not comply, the market surveillance authority sets out that evidence to the economic operator and gives it a time limit to submit observations and the corrective measures envisaged, specifying their nature, how they will be implemented, the timetable for their deployment, how users will be informed and who bears the cost (Labour Code, Article R. 4314-10, I). The authority may also require the manufacturer to have the proposed measures checked, at its own expense, by an accredited body other than the one that assessed conformity before the product was placed on the market (II).

Give one date per product, calculated from the date the complete file was sent and stated "subject to test results". Asking for a time limit per product is usually more realistic than a single time limit for the whole catalogue. The signed quote, proof of payment, proof of shipping and the body's acknowledgement of receipt make the date credible; the authority may in any event ask for documents, as explained in our article on the DGCCRF request for documents under Article L. 512-8. If a date cannot be kept, inform the authority before it expires, with the reason and a new realistic date. The wording of that letter is a matter for case-by-case advice.

Table 3 - Product-by-product tracking table (fictitious example)

Product Complete file received Estimated end of testing Estimated certificate Date given to the authority Documents attached
Product A 30/11/2026 Around 03/02/2027 Around 17/02/2027 End of February 2027, subject to test results Signed quote, proof of payment, acknowledgement of receipt
Product B 04/01/2027 Around 08/03/2027 Around 22/03/2027 End of March 2027, subject to test results Signed quote, proof of payment, acknowledgement of receipt
Product C File in preparation - - Date given once the complete file is sent Signed quote, list of missing documents

Step 7 - Say nothing to consumers before the certificate

Until the EU type-examination certificate is issued, category II PPE can carry neither the CE marking nor an EU declaration of conformity (Articles 8(2) and 17). Statements such as "certification in progress" (en cours de certification), "CE pending" or "certified by" followed by a body's name should not appear on the website, product pages, packaging or instructions. Non-compliant CE marking is a fifth-class petty offence (Labour Code, Article R. 4746-1), and a statement suggesting that certification has been obtained could also be treated as a misleading commercial practice. If the case escalates to a fine, our guide on how to challenge a DGCCRF fine in France describes the remedies.

After the certificate: Module C, declaration and renewal

Once the certificate is issued, the manufacturer ensures that production stays in conformity with the examined type, affixes the CE marking to each conforming item and draws up a written EU declaration of conformity for each model, kept for ten years (Annex VI). The certificate, its annexes and the technical documentation are kept available to the authorities for ten years after the PPE is placed on the market (Annex V, point 9). An EU type-examination certificate is valid for five years at most (Annex V, point 6.1, and recital 27). The review application must be lodged no earlier than twelve months and no later than six months before expiry (point 7.4), and any modification that may affect conformity requires additional approval (point 7.2).

Frequently asked questions

When does the notified body's lead time start?

On the date set by the body's terms, usually receipt of everything requested: samples, technical documentation, instructions and payment. Signing the quote is not enough, and the regulation itself sets no processing time.

Can the whole catalogue be certified at once?

Nothing prevents it, but cost, samples and the body's capacity often lead to one or two products a month, about six months for ten product references (order of magnitude).

What date should be given to the authority?

One date per product, counted in working days from receipt of the complete file, stated "subject to test results" and supported by the quote, proof of payment and proof of shipping.

Can "certification in progress" be written on PPE?

No. Before the certificate, category II PPE can carry neither the CE marking nor any statement suggesting certification, and it stays off sale.

Conclusion

The timeline of an EU type-examination runs from a complete file received by the notified body, counted in working days. Checking the body in NANDO, reading its terms, shipping a complete file, staggering products and giving one date per product subject to testing make it possible to keep the dates given to the authority. If you have received a letter from the DDPP about PPE, our page on DGCCRF and DDPP inspections explains how the firm can assist.

Guillaume Leclerc, avocat at the Paris Bar, Victoris law firm, 34 avenue des Champs-Élysées, Paris.

Further reading: