After a DGCCRF or DDPP inspection in France: build a dated compliance plan, set realistic deadlines, handle a slipping date and prove each step.

The inspectors have visited your shop, your warehouse or your website, and a letter has followed: a warning, a letter announcing an injunction, an injunction already issued, or a proposed administrative fine. The same question then lands on the manager's desk: what must be corrected, in what order, by when, and how should the authority be told? The French consumer protection authorities, the DGCCRF (Direction générale de la concurrence, de la consommation et de la répression des fraudes) and its local offices, the DDPP (Directions départementales de la protection des populations), can do little with a sentence such as "we will bring our practices into line". What they can check is a compliance plan: a list of measures taken finding by finding, each with an owner, a date and the evidence that will be supplied.
That document weighs on the rest of the case because almost every tool available to the authority runs on a time limit. An injunction under Article L. 521-1 of the Consumer Code (Code de la consommation) gives the trader a "reasonable time limit" and may carry a daily penalty. Measures targeting products are carried out within a period set by the authority. An administrative fine is preceded by a one-month adversarial procedure, during which the company can show what it has already fixed. A date promised and kept gives weight to every other commitment. A date that slips without warning has the opposite effect, and the authority remembers it when it decides what happens next.
This guide is written for managers of small and mid-sized businesses (online sellers, importers, own-brand companies) under inspection or holding one of those letters. It covers what the authority expects at each stage, what a credible plan contains, how to set realistic dates, what to do when a deadline is at risk and how to prove performance, with a fictitious example and three tables. Because the plan commits the company through what it promises and what it says, this is one of the points where our work as a lawyer on DGCCRF and DDPP inspections makes the most difference.
The DGCCRF itself sorts the outcomes of an inspection into three families. Educational outcomes take the form of a warning, used for minor breaches caused by ignorance of the rules or light negligence. Corrective outcomes cover injunctions and administrative police measures on products or premises. Punitive outcomes include administrative fines, a report sent to the public prosecutor, or a settlement. In an interview published on the French Ministry of the Economy website, a DGCCRF deputy director explains that corrective and punitive outcomes can be combined: a company may be ordered to stop a practice and fined for past conduct.
Under Article L. 521-1 of the Consumer Code, officials who find a breach may, after an adversarial procedure, order the trader to comply with its obligations, stop any unlawful conduct or remove any unlawful clause, within a reasonable time limit that they set themselves. The injunction may carry a daily penalty (astreinte) of up to EUR 3,000, capped at EUR 300,000 in total. Where the breach is punishable by a fine of at least EUR 75,000, the daily penalty may instead be based on worldwide turnover excluding VAT for the last closed financial year, up to 0.1% per day, with a total cap of 5%.
The penalty runs from the day after the time limit expires, and the authority may enforce it, after hearing the company, in case of total or partial failure or late performance. Late performance is therefore covered expressly, in the same way as refusal. The injunction may also be published at the trader's expense (Article L. 521-2). When the time limit expires, a follow-up inspection takes place. If the company merely wrote that it would "review its practices as soon as possible", the inspector has nothing to check and sets the timetable without knowing the company's constraints. A plan with measures, dates and evidence gives the inspector a checklist instead.
A warning explains the breaches found, the applicable rules and the penalty incurred. It does not always set a deadline, but the DGCCRF states that a further inspection is to take place in the months following the warning and that, if the breach is found again, firmer action follows. The company should correct at once and keep dated evidence of its corrections. Whether to reply in writing depends on the points in dispute: a badly judged reply can admit more than the authority had found.
Before issuing an injunction, the authority must hear the company (Article L. 521-1). In practice, it sends a letter announcing the measures it intends to order, often called a pre-injunction letter, and gives the company time to respond. That period is not set by Article L. 521-1 itself: it is stated in the letter. According to the DGCCRF, the company may use this phase to dispute the findings or to change its conduct, which may lead the authority not to issue the injunction or to narrow it. This is often when a compliance plan has the most effect: showing what has been fixed, what remains and by when, with evidence and verifiable constraints, gives the authority the means to adjust its decision.
Where it is established that products do not comply with the rules or present, or may present, a danger to public health or consumer safety, the authority may issue an order (arrêté) suspending their placing on the market or requiring their withdrawal, recall and destruction and, where there is a danger, the issue of warnings and a recall for exchange, modification or refund (Article L. 521-7). Any operator who bought or sold the products and knows of the decision must inform its supplier and the operators it sold to (Article L. 521-9). Officials may also order the products to be brought into conformity at the operator's expense "within a time limit they set"; if that is impossible, the authority may order another use, re-export or destruction (Article L. 521-10).
Where there are doubts about a product's safety compliance and the operator cannot show the checks it carried out, the authority may order testing by an independent body at the operator's expense within a set period, suspend sales in the meantime and require the cost to be deposited (Article L. 521-12); if the testing is not done in time, it may be carried out at the operator's expense (Article L. 521-13). For products covered by EU harmonisation legislation, Regulation (EU) 2019/1020 on market surveillance provides that authorities require the operator to take appropriate and proportionate corrective action within a period they specify (Article 16). The plan then becomes a technical timetable. Failing to carry out these measures is a criminal offence punishable by two years' imprisonment and a EUR 15,000 fine, with a higher amount in some cases (Article L. 532-3).
Before imposing an administrative fine, the authority informs the company in writing of the penalty it intends to impose, tells it that it may be assisted by counsel of its choice and invites it to submit written and, where applicable, oral comments (Article L. 522-5). The period is one month (Article R. 522-2). After that, the fine may be imposed by a reasoned decision. The same authority also fines failures to comply with injunctions (Article L. 522-1). During that month, the plan documents what has been done since the inspection. The DGCCRF lists immediate remediation among the criteria it considers, alongside the seriousness and impact of the facts and any intention to defraud.
The authority may also, together with the notice of the proposed fine, offer an administrative settlement (transaction administrative), which suspends the one-month period (Article L. 522-9-1). The amount payable takes into account the commitments made by the company and is lower than the maximum fine. The agreement may include obligations to stop the breaches, prevent their repetition and compensate consumers. If there is no agreement, no payment or a failure to meet those obligations, the sanction procedure goes ahead.
The starting point is the authority's document: warning, pre-injunction letter, injunction, order or proposed fine. The plan follows its findings in the same order and numbering, one line per finding. The inspector can then see the answer to each point at a glance, and the company can check that nothing has been missed. Grouping several findings under a vague heading ("website update") leaves the authority to guess what is covered. Some findings are accurate and easy to fix; others are open to dispute, and the company may want to challenge them while acting as a precaution. How to handle both in one document is a drafting choice that depends on the case, and one where a lawyer's input changes the quality of the plan most.
Some measures can be taken within days: removing a disputed claim, switching off a price reduction banner, suspending sales of a product, quarantining stock, correcting a clause in the terms of sale. They limit consumers' exposure while longer work progresses, and they let the company propose realistic dates for the substantive fixes. Other measures take weeks because they depend on third parties: new label or leaflet mock-ups, technical files from the manufacturer, further laboratory testing, translations, new terms of sale, internal procedures, staff training. The plan should also deal with what has already left the business: stock held by resellers or on marketplaces, products already sold, consumer contracts concluded on non-compliant terms.
Each measure needs an owner identified by role and a calendar date. "The company" is not an owner, and "within a fortnight" is not a date, because nobody knows when it starts. The last column is the evidence: time-stamped screenshot, invoice, test report, label photograph, signed procedure. "Improve consumer information" cannot be proved; "publish the corrected terms of sale, clause 7 amended, time-stamped screenshot" can. A measure whose proof cannot be described is usually poorly defined.
Fictitious example: a small company sells household linen, decorative tableware and scented candles online, partly imported from a supplier outside the EU. After an online inspection and a request for documents, the DDPP sends a letter announcing an injunction and listing four findings: price reductions without a justified reference price; a "Made in France" claim on cushions sewn abroad; terms of sale with incomplete information on the right of withdrawal and no consumer mediator; and a range of imported candles whose labels lack certain safety warnings and the importer's full contact details. The company has no legal or quality department. Its printer needs about ten working days, its supplier two to three weeks to send technical information, and joining a mediation scheme takes its own processing time.
Within two days, the company removes the disputed price reductions and the origin claim, takes the candles offline and has the stock quarantined by its logistics provider, keeping time-stamped screenshots. Within ten days, it publishes corrected terms and applies to a mediation scheme. For the candles, it obtains the information from the supplier, prepares a label mock-up, has it approved and printed, relabels the quarantined stock and only then resumes sales. The label dates are based on the lead times confirmed in writing by the supplier and the printer, plus a week's margin. In the table below, dates run from the day the letter was received (D); in a real plan, each one is a calendar date.
The example separates the measures that protect consumers at once from those that take time, which allows longer dates without leaving the problem open. Each date accounts for an identified third party whose lead time is on file. The evidence is planned from the outset. The plan also says nothing about the legal characterisation of the facts: the company describes what it does without commenting on what it is accused of, a point dealt with in its comments, with counsel.
Most delays come from third parties whose dates were not checked before being promised to the authority: a supplier late with a certificate, a laboratory whose unfavourable report requires a new test, a printer, translator, web agency, marketplace or mediation scheme working to its own schedule. Before writing a date, ask each of them and get a written answer giving a date or a duration. That answer lets you set a realistic deadline and, if the date later slips, shows that the delay was not the company's negligence.
A date that is too close will be missed, and a first delay weakens every other commitment. A date that is too distant may be rejected by the authority, which controls the injunction's time limit, and leaves consumers exposed for longer. The usual answer is to pair an immediate protective measure with a later date for the substantive fix. The margin must reflect the real calendar: public holidays, summer and year-end closures, factory shutdowns in Asia around the Lunar New Year, shipping times. Long measures should be split into milestones (samples sent, tests started, report received; mock-up, approval, printing, application), each with its own date, so that progress can be reported and delays spotted early.
A date can slip for good reasons. What changes the authority's view is when it finds out. A delay announced before the due date, explained, with a new date and proof of progress, shows a company in control of its remediation. The same delay discovered at the follow-up inspection shows a company that let a date pass in silence. Inspection files show it again and again: a promised date that slips without warning damages the whole discussion, and the authority starts to doubt every other commitment.
The message recalls the commitment, states what has been done, explains the cause of the delay with the supporting document attached (the laboratory's, supplier's or printer's email), proposes a precise new date and confirms that the protective measure stays in place. It goes in writing to the official handling the file, with proof of sending. Where the date is set by an injunction, the daily penalty may run from the day after the time limit expires, so the message must leave early enough for the authority to respond, and its wording matters because it will be reread if the penalty is enforced. Whether and how to ask for more time should be decided with a lawyer.
After an injunction, failure or late performance exposes the company to enforcement of the daily penalty (Article L. 521-1) and to an administrative fine for non-compliance of up to EUR 15,000 for an individual and EUR 75,000 for a company, raised to the fine incurred for the original breach where that is higher (Article L. 532-1). For product measures, non-performance is an offence under Article L. 532-3. Silence becomes more dangerous when the company stops answering altogether. Officials may require any document useful to their task (Article L. 512-8; see our guide to DGCCRF requests for documents), and obstructing them is prohibited (Article L. 512-4). Obstruction is punishable by two years' imprisonment and a EUR 300,000 fine, which may be raised, in proportion to the benefit gained, to 10% of average annual turnover (Article L. 531-1). In our view, a delay in carrying out a plan is not obstruction in itself; ceasing to respond to the inspector's requests can be.
A measure carried out without evidence is, for the authority, a measure it knows nothing about. Useful evidence includes time-stamped screenshots showing the page address and date, before and after; invoices from the laboratory, printer or provider; test reports; photographs of new labels and relabelled stock; a mediation scheme membership certificate; signed internal procedures; training attendance sheets. For major website changes, a report drawn up by a commissaire de justice (judicial officer) carries more weight than a screenshot. Each exhibit is numbered and cross-referenced in the evidence column.
As the work progresses, the plan becomes a tracking table: planned date, actual date, status and evidence reference for each line. The person running the remediation updates it weekly if possible. It is sent to the authority at the stages announced in the plan and whenever a date changes.
Bringing a practice into line does not in itself amount to admitting the breach: a company may correct a claim as a precaution while disputing that it was unlawful. That distinction only holds if the wording respects it. A plan that describes the facts in the company's own words, explains why the breach occurred, gives sales figures or concedes that a practice "was not compliant" hands the authority material it may not have had. That material will be reread when a fine is considered and, if a report goes to the public prosecutor, before the criminal court. Drafting the plan is therefore part of the company's defence.
Fast, documented remediation does not remove the fine for past conduct, but the DGCCRF counts immediate remediation among its criteria. The fine is set within the maximum laid down for the breach, and its proportionality can be discussed; our article on challenging a DGCCRF fine explains the options.
An injunction is an administrative decision that can be challenged before the administrative court, as a rule within two months of notification (Article R. 421-1 of the Code of Administrative Justice, Code de justice administrative). The challenge does not suspend the decision unless a specific statute provides otherwise or the court so orders (Article L. 4 of the same code). In most cases, the company must keep complying while the case is pending, so the plan and the court filing must be consistent. This is precisely where a lawyer on DGCCRF and DDPP inspections adds the most: remediation happens anyway, and the difference lies in what is promised, what is written and when it is said.
The plan has no required form, and the Consumer Code provisions on the follow-up to inspections do not require it to be sent unprompted. The authority often asks for one, expressly or by inviting the company to state the measures taken. Where it does not, a plan can help during the adversarial phase before an injunction or a fine. When to send it and what it should say depend on the case: a plan sent too early or badly drafted commits the company with nothing in return.
There is no single period. For an injunction, Article L. 521-1 provides for "a reasonable time limit" set by the officials. For product measures, the authority sets the period in its decision (Articles L. 521-10 and L. 521-12). The period to answer a proposed administrative fine, by contrast, is fixed by regulation at one month (Article R. 522-2). That is why the company's real constraints, with supporting documents, should be put to the authority before the injunction's time limit is set.
A request can be made, but there is no right to an extension. It stands a better chance if it is sent before the time limit expires, explains the cause of the delay with evidence, proposes a precise date and shows what has already been done. Without an answer from the authority, nothing suggests that the time limit has been extended, and any daily penalty runs from the day after it expires.
The daily penalty may be enforced for total or partial failure or late performance (Article L. 521-1), up to EUR 3,000 per day and EUR 300,000 in total, or 0.1% of worldwide turnover per day and 5% in total for breaches punishable by at least EUR 75,000. An administrative fine for non-compliance may also be imposed, up to EUR 15,000 for an individual and EUR 75,000 for a company, or the fine for the original breach if higher (Article L. 532-1). The original breach can still be fined, and failure to carry out product measures is a criminal offence (Article L. 532-3).
No. Remediation looks to the future and does not erase past breaches: the authority may issue an injunction for the future and a fine for past conduct. The DGCCRF does, however, take immediate remediation into account when choosing its response, so documented remediation belongs in the company's written comments, alongside arguments on the merits and on the proportionality of the amount.
Yes. When it notifies a proposed fine, the authority may offer a settlement under Article L. 522-9-1 of the Consumer Code. The amount takes into account the company's commitments, and the agreement may include obligations to stop the breaches, prevent their repetition and compensate consumers. If those obligations are not met, the sanction procedure goes ahead, so the commitments must be dated and achievable.
After a DGCCRF or DDPP inspection, the authority expects steps, dates and evidence. A compliance plan that takes each finding with a measure, an owner, a calendar date and the planned evidence lets the authority check and lets the company manage its corrections. Dates are set after asking suppliers, laboratories, printers and providers, with a margin and milestones, while protective measures shield consumers. When a date is at risk, the authority should hear it from the company, before the due date, with an explanation, a new date and proof of progress. What the plan says will be reread when a fine is considered. If you have just received a warning, a pre-injunction letter, an injunction or a proposed fine, the firm can help you build a realistic plan, present it to the authority and follow it through until the file is closed.
Guillaume Leclerc, avocat at the Paris Bar, Victoris law firm, 34 avenue des Champs-Élysées, Paris.
Further reading: