B2B payment terms in 2026: 30 days, 60 days, or 45 days end-of-month, sector-specific deadlines, penalties, and the €40 fixed indemnity.

The B2B payment terms are governed by a set of precise rules set out in Articles L. 441-9 to L. 441-16 of the French Commercial Code. These establish the default deadline in the absence of an agreement, the maximum deadline parties may agree upon, specific deadlines for certain sectors, the date on which an invoice is deemed paid, as well as the penalties and indemnity due in the event of late payment. These rules are mandatory: a supplier cannot validly agree to be paid beyond these limits, and a client cannot bypass them through their own purchasing terms.
This is not an abstract issue. In 2025, the DGCCRF inspected 882 establishments, identified irregularities in 54.2% of cases, and issued €59.1 million in fines, an increase of 65%, according to the report from the Payment Terms Observatory published in September 2026. Fines can reach €2 million per breach for a legal entity, and every decision is published naming the company involved. In many inspection files, the delays identified stem from a misunderstanding of the rules themselves: miscalculated deadlines, unenforceable clauses, or misidentified sectors.
This guide outlines the rules in force as of October 3, 2026: the default deadline, agreed-upon deadlines, specific and sector-based regimes, payment dates, penalties, information to be included in management reports, and the framework for sanctions. If your company is already under investigation, our team specializing in DGCCRF, DDPP, and DREETS audits can assist you from the moment you receive the opening letter.
The current regime stems from the Law on the Modernization of the Economy of August 4, 2008, overhauled by Ordinance No. 2019-359 of April 24, 2019, and subsequently supplemented by Ordinance No. 2021-859 of June 30, 2021. Its purpose is to protect the cash flow of suppliers, who are often smaller than their clients, against imposed supplier credit. The DGCCRF stated this clearly in its FAQ of October 25, 2024: as regulations on payment terms are public policy, it is not possible to derogate from this by contract, and the supplier's agreement to be paid later is null and void.
Two practical consequences follow from this. Firstly, an average payment period below the ceiling does not cover invoices paid late: every instance of exceeding the limit is a breach, and early payments do not compensate for anything. Secondly, the absence of intent does not change the material nature of the breach: good faith does not constitute grounds for exemption.
The rules apply to all payments made under contracts for the sale of goods or the provision of services between entities engaged in economic activity, including when this activity is carried out by a public entity. They target all forms of businesses, from joint-stock companies to sole proprietorships. Public procurement contracts are subject to the overall payment period provided for by the Public Procurement Code, which follows separate rules.
International contracts raise a specific issue: the law applicable to the contract, within the meaning of the European "Rome I" regulation, may or may not lead to the exclusion of French law. The answer depends on the drafting of the contract, the location of the parties, and the classification of the rules in question. This analysis is done on a case-by-case basis and should be conducted before an audit forces you to do so.
Ordinance No. 2026-671 of July 27, 2026, amends Articles L. 441-9 and L. 441-10 effective January 1, 2027, primarily to replace references to the General Tax Code with references to the Code of Taxes on Goods and Services. The deadlines themselves do not change: 30 days in the absence of an agreement, 60 days or 45 days end-of-month if agreed upon, and 45 days for periodic invoices. A substantive reform is, however, being discussed in Parliament (see below the bill adopted by the Senate on February 19, 2026).
Article L. 441-10, I, paragraph 1 of the Commercial Code states: "Unless otherwise provided in the terms of sale or agreed between the parties, the payment period for sums due may not exceed thirty days after the date of receipt of the goods or the performance of the requested service." This is the supplementary period : it applies as soon as the parties have not provided for anything valid, and it does not run from the invoice date but from the date of delivery or performance.
Because it runs from the receipt of goods or the performance of the service, the supplementary period requires reconstructing a factual date: signed delivery note, acceptance report, proof of completion of work. An invoice issued late by the supplier does not push back the deadline. Conversely, a buyer who does not receive an invoice must request one: Article L. 441-9 makes this an obligation, and the DGCCRF will only disregard a late-received invoice if the buyer proves they followed up before the deadline.
Many companies think they are applying a 60-day period because their general terms of purchase provide for it. However, these terms must be enforceable against the supplier: written in a language they understand, brought to their attention before the order, and accepted. Purchase terms accessible only via a simple link on a purchase order, or contradicted by the supplier's terms of sale, may not be sufficient. The applicable period then reverts to the 30-day supplementary period.
The difference is significant. Take a company that pays 1.2 million euros in invoices 75 days after they are issued. With an agreed period of 60 days, the delay is 15 days. Without an enforceable agreed period, and with deliveries close to the invoice date, the ceiling becomes 30 days and the delay increases to 45 days: the cash retention, which serves as the basis for calculating the fine, is tripled. Checking your terms of purchase and sale is the first thing to do, and our page dedicated to the general terms and conditions of sale and purchase outlines the support provided on this matter.
When the parties set the deadline themselves, Article L. 441-10, I, paragraph 2 sets the cap: "The deadline agreed between the parties to settle the sums due may not exceed sixty days after the invoice issue date." The count is made in calendar days, from date to date, including weekends and public holidays. A shorter deadline can obviously be agreed upon, and this is common: 30 days, or even payment upon delivery.
The starting point is the invoice issue date. Hence the importance of ensuring that the date recorded in the accounting system is the one appearing on the invoice, rather than the date of entry or reconciliation with the order. During an audit, the authorities start from the dates in the supplier ledger: an entry date later than the invoice date makes payments appear faster than they actually are, which investigators verify using a sample of invoices.
The same article allows, "by way of derogation," a maximum deadline of 45 days end of month after the invoice issue date, subject to two conditions: that it is expressly stipulated by contract and that it does not constitute a manifest abuse with regard to the creditor. Two calculation methods are accepted, which the authorities themselves present on the Service Public Entreprendre website:
The parties must agree on the method used. In practice, during an audit, the authorities measure the delay based on the method most favorable to the company being audited, but ambiguous wording remains a source of dispute with suppliers and does not protect against overruns beyond the longest method.
The phrase "60 days end of month" still appears in many purchasing terms and conditions. It is not provided for by any legal text. Depending on the invoice issue date and the calculation method, it can lead to payment up to 90 days after issuance, which is well beyond the only two permitted caps: 60 days net or 45 days end of month. Any invoice settled according to this formula beyond these caps constitutes a breach.
Some clauses trigger the payment period not from the invoice date, but from its receipt, internal validation, or the latest of several dates. Article L. 441-16 prohibits, under the same penalties as exceeding payment deadlines, "any clauses or practices that have the effect of abusively delaying the start of payment periods." The DGCCRF FAQ adds that difficulties related to internal invoice processing are irrelevant: the supplier should not have to suffer the consequences of their client's internal organization.
When a supplier issues a periodic invoice, meaning an invoice summarizing several distinct deliveries or services performed during the same calendar month, the agreed period cannot exceed 45 days after the invoice date (Article L. 441-10, I, paragraph 4). This cap is shorter than the 60-day limit because the first deliveries of the month have already been completed several weeks prior by the time the invoice is issued.
This regime applies to many sectors: energy, telecommunications, equipment rental, recurring services, and subscriptions. A company that mistakenly applies the 60-day cap to its periodic invoices will be in breach on all of them, which becomes immediately apparent when analyzing the general ledger by payment term type.
When a contract provides for a procedure to verify the conformity of goods or services, its duration cannot exceed 30 days from the receipt of the goods or the completion of the services, unless otherwise expressly stipulated in a way that does not constitute an abusive clause or practice (Article L. 441-10, III). Crucially, this procedure cannot extend the payment period or delay its start date, unless expressly stipulated and non-abusive. A drawn-out acceptance process does not, therefore, push back the invoice due date.
By way of derogation, the agreed period for purchases made VAT-free, pursuant to Article 275 of the General Tax Code, for goods intended to be delivered as-is outside the European Union may be up to 90 days after the invoice date (Article L. 441-12). The period must be expressly stipulated and must not constitute a manifest abuse. This derogation does not apply to purchases made by large companies, and late payment penalties become due again if the goods are not used for their intended purpose.
For goods imported into overseas departments and certain overseas collectivities (Guadeloupe, Martinique, French Guiana, Réunion, Mayotte, Saint Barthélemy, Saint Martin, Wallis and Futuna, Saint Pierre and Miquelon), the periods are only counted from the date of customs clearance at the final port of destination. If the goods are made available to the buyer in mainland France, the period runs from the twenty-first day following this availability, or from customs clearance if it occurs earlier (Article L. 441-13).
Article L. 441-11, II sets shorter deadlines from which the parties cannot derogate:
The 5th paragraph of the same article sets the deadline at 30 days after the invoice issue date for road freight transport, vehicle rental with or without a driver, transport brokerage, as well as freight forwarding, shipping agency, air freight, freight brokerage, and customs brokerage activities. This is the deadline that results in the most violations: many companies apply their general 60-day deadline to their carriers by default.
Classification is determined on a service-by-service basis. An invoice for storage, order picking, or comprehensive logistics services does not necessarily fall under the 5th paragraph, whereas an invoice for pure transport does. During an audit, classification is based on the list of suppliers and their "typology," which the company itself provides to the authorities: a classification error at this stage affects all invoices from the supplier in question.
Conversely, some sectors benefit from longer deadlines, provided these are expressly stipulated in the contract and do not constitute a manifest abuse; otherwise, the 60-day deadline applies (Article L. 441-11, III). This applies to: agricultural equipment (55 days end-of-month for green space maintenance equipment, 110 days end-of-month for certain agricultural machinery), snow sports equipment delivered before the season (90 days for the balance), the leather industry (54 days end-of-month), watchmaking, jewelry, and goldsmithing (59 days end-of-month or 74 days net), and toys (95 days net from January to September, 75 days net from October to December).
Professionals in a sector may also decide together to reduce the maximum deadline or to use the date of receipt of goods as the starting point, through agreements concluded between professional organizations that a decree may extend to the entire sector (Article L. 441-11, I). Before setting your payment terms, it is therefore useful to check whether any extended agreement applies to your business.
Article L. 441-9 of the French Commercial Code settles the matter: "Payment is deemed to have been made on the date on which the funds are made available to the beneficiary or their subrogee by the client." Therefore, it is not the date of the transfer order, the date the client's account is debited, or the accounting date that counts, but the date on which the supplier actually has access to the funds. A transfer issued on the due date can thus result in a delay of one or two days.
However, many accounting systems record the transfer issuance date. The difference may seem minimal, but it applies to all invoices for the financial year and can cause invoices paid at the very end of the deadline to be classified as late.
A company that pays its suppliers once a week mechanically creates delays of one to six days on invoices whose due dates fall between two payment cycles. Even when the authorities move a due date falling on a Saturday, Sunday, or public holiday to the next business day, this extension applies to the due date, not to the internal payment schedule. Consider 8 million euros in invoices settled on average three days after the due date: the cash retention amounts to approximately 66,000 euros over the year, without any intention to delay.
The mention of a "subrogee" specifically refers to factoring companies and institutions that finance supplier receivables. In reverse factoring arrangements, where a financial institution pays suppliers on behalf of the buyer, the authorities closely examine the contracts, the date actually used, and the question of who decides the payment date. These structures require specific analysis before any audit, and it is precisely at this stage that guidance from a lawyer specializing in payment terms makes the difference.
Payment terms must specify the rate of late payment penalties, which are due the day after the payment date shown on the invoice (Article L. 441-10, II). In the absence of a stipulated rate, this rate is equal to the European Central Bank's refinancing rate plus 10 percentage points: the rate in effect on January 1st applies to the first half of the year, and the rate on July 1st applies to the second. The agreed rate cannot be lower than three times the legal interest rate.
In practical terms, the standard late payment penalty rate is 12.15% for the first half of 2026 and 12.40% for the second half of 2026, according to Service Public Entreprendre. A 50,000-euro invoice paid 30 days late in the second half of 2026 would therefore generate approximately 510 euros in penalties. These penalties are due without the need for a reminder.
Any professional who is late with a payment must also, by right, pay a fixed indemnity of 40 euros per invoice (Article D. 441-5 of the Commercial Code). If the actual recovery costs incurred are higher, the creditor may request additional compensation upon justification. These indemnities cannot be claimed when the opening of safeguard, reorganization, or judicial liquidation proceedings prohibits the payment of the debt at its due date.
The calculation of these sums follows precise rules which we detail in our guide on calculating late payment penalties.
The penalty rate and the amount of the indemnity must appear in the general terms and conditions of sale and on each invoice, which must also state the date by which payment must be made (Articles L. 441-9 and L. 441-10, II). The absence of this information, or a non-compliant rate, constitutes an autonomous breach, punishable by the same administrative fine as exceeding payment deadlines (Article L. 441-16, b and c). Breaches of invoicing rules are also subject to a fine of up to 375,000 euros for a legal entity (Article L. 441-9, II).
Companies whose annual accounts are certified by a statutory auditor must provide information on the payment deadlines of their suppliers and customers, according to procedures set by decree (Article L. 441-14). In practice, this information takes the form of tables included in the management report, which list, in particular, invoices received and issued that remain unpaid at the closing date and are past their due date.
This information is subject to certification by the statutory auditor. When the company is a large enterprise or an intermediate-sized enterprise, the statutory auditor "shall send their certification to the Minister for the Economy if it demonstrates, repeatedly, significant breaches" of the ceilings set out in Article L. 441-10, I or the transport deadline (Article L. 441-14, paragraph 2). This mechanism remains rarely used, due to the lack of a legal definition of what is "significant" and "repeated."
A bill aimed at reducing payment delays was adopted by the Senate on February 19, 2026, and transmitted to the National Assembly. The text adopted by the Senate would raise the fine ceiling for a legal entity to the higher of 2 million euros or 1% of global turnover, would extend the repeat offense period from two to three years, would require the statutory auditor's certification to be sent to the Minister after two consecutive years of exceeding deadlines, and would make deadlines run from the receipt of the invoice starting in 2030. At this stage, this is only a proposal: the applicable law remains the one described in this guide.
Article L. 441-16 punishes with an administrative fine of up to 75,000 euros for a natural person and 2 million euros For a legal entity, this includes failure to comply with statutory deadlines, omission of mandatory information in payment terms, non-compliant penalty rates, and failure to adhere to agreed-upon calculation methods. The cap is increased to 150,000 euros, and up to 4 million euros in the event of a repeat offense within two years of a final sanction. According to the DGCCRF FAQ, when multiple types of deadlines are involved, fines are calculated separately for each.
The decision is published on the DGCCRF website and in a legal notice publication, at the company's expense. The fine amount is based on the cash flow retention generated by the delays; we detail this calculation, the adversarial phase, and the appeals process in our guide on theDGCCRF fine for payment delays.
Audits are conducted by the DREETS on behalf of the DGCCRF. They generally cover the most recently closed financial year and are based on the dates in the supplier ledger, supplemented by a sample of invoices and proof of payment. The company submits its accounting files, a list of its suppliers categorized by type, and its tax returns; its representatives are then interviewed, and their statements are recorded in the minutes. The full process is outlined in our article on the audit of payment delays by the DGCCRF.
In certain sectors defined by decree, where rules raise specific difficulties, a professional may ask the administration to take a formal position on the compliance of the deadline calculation methods they intend to implement (Article L. 441-15). This position protects them from a change in the administration's assessment as long as their situation and the relevant texts remain unchanged. Preparing such a request, as well as bringing your payment terms into compliance, is best handled with a lawyer specializing in payment delays.
In the absence of an agreement, the deadline is 30 days after receipt of goods or performance of services. If the parties agree on a deadline, it cannot exceed 60 days after the invoice date, or 45 days end-of-month, provided this is expressly stipulated and not abusive. Periodic invoices are limited to 45 days after issuance, and several sectors have specific, shorter (transport, food) or longer (toys, watchmaking, leather, agricultural equipment) deadlines.
No. The Commercial Code provides for only two contractual caps: 60 days net after the invoice date, or 45 days end-of-month. The "60 days end-of-month" formula can lead to payment up to 90 days after issuance: any invoice paid beyond the statutory caps constitutes a breach subject to the administrative fine under Article L. 441-16.
Two methods are accepted. Either you go to the end of the month in which the invoice was issued and add 45 days, or you add 45 days to the issue date and go to the end of the resulting month. For an invoice dated August 1, 2026, the due date is October 15, 2026, using the first method, and September 30, 2026, using the second. The parties must agree on which method is used.
The deadline cannot exceed 30 days after the invoice date for road freight transport, vehicle rental with or without a driver, transport brokerage, and the activities of freight forwarders, shipping agents, air freight agents, freight brokers, and customs brokers (Article L. 441-11, II, 5°). This deadline is mandatory, regardless of the general deadline provided for in your purchasing terms.
Yes. Late payment penalties are due the day after the payment date shown on the invoice, without the need for a reminder, and the 40-euro fixed indemnity is automatically due for every invoice paid late. The creditor may claim additional compensation if they can justify higher recovery costs.
No, except in cases provided for by law (purchases intended for export outside the European Union, certain specific sectors). Payment deadlines are a matter of public policy: the supplier's agreement does not negate the breach, and the DGCCRF expressly rejects it as a justification during audits.
On the date the funds are made available to the supplier or their subrogee (Article L. 441-9). Therefore, it is the date the funds are credited to the supplier that counts, not the date of the transfer order or the date it is recorded in the client's accounts.
The terms will not change on January 1, 2027: the ordinance of July 27, 2026, merely replaces certain references to the General Tax Code with references to the Code of Taxes on Goods and Services. A more significant reform is currently being discussed in Parliament, which includes a fine cap of 1% of global turnover and a start date based on the receipt of the invoice starting in 2030, but it has not been adopted to date.
The rules on payment terms between businesses can be summarized in a few figures: 30 days in the absence of an agreement, 60 days or 45 days end-of-month at most if agreed upon, 45 days for periodic invoices, 30 days for transport, and specific deadlines for the food industry and certain other sectors. Difficulties rarely stem from the figures themselves. They arise from an unenforceable purchase clause, a misclassified supplier, an incorrectly recorded payment date, or a payment cycle that is poorly aligned with due dates—all of which are errors that can be repeated across every invoice in a fiscal year.
The Victoris firm assists finance and legal departments in reviewing their payment terms, preparing for audits by the DGCCRF and DREETS, and providing defense in the event of proposed sanctions. If you would like to verify your practices or if an audit has just been initiated, we can discuss it during an initial consultation.
Article written by Guillaume Leclerc, business lawyer in Paris, 34 Avenue des Champs-Élysées.